Reimagine Dumbarton's vision is to transform a former freight rail line into a busway and trail for walking and bicycling spanning about 5 miles between Redwood City and East Palo Alto on the Peninsula.
Community engagement is happening now! Check out the Get Involved tab below for information on community events.
Reimagine Dumbarton
SamTrans is reimagining the unused Dumbarton freight railroad line to bring fast, reliable, zero emission bus service and improvements for people biking and walking to the communities of Southeast San Mateo County including East Palo Alto, Menlo Park, Redwood City, Atherton, and North Fair Oaks.
Study Area:
Post-pandemic travel patterns show people are making more local trips. The average daily travel between Redwood City and East Palo Alto has increased by more than 30% since 2019. Reimagine Dumbarton presents an opportunity to create a community-driven project that uses zero emission technology to provide fast and reliable transit connections and foster healthy and sustainable communities.
Survey open now! Provide feedback through October 30!
Current state of the Dumbarton Corridor, 2025
How the Dumbarton Corridor Could Look
Stakeholder Engagement
Between fall 2025 and winter 2026, the project team analyzed existing conditions and conducted Phase 1 of community engagement. More than 1,000 community members shared their transportation needs and priorities through surveys, community meetings, and pop-up events. This stakeholder input, together with technical analysis, informed the preliminary alternatives now ready community to review. Please click on the “Project Design Proposals” tab for more information on the proposed designs and take our survey by October 30 to give your input!
Reimagine Dumbarton is currently in the feasibility study phase. The feasibility study will take place from fall 2025 to spring 2027, with multiple community engagement opportunities.
The Reimagine Dumbarton project’s design proposals include dedicated space for enhanced transit service, walking and bicycling on a paved trail, and improved public access and community spaces.
Fast, reliable and frequent transit
Reimagine Dumbarton includes a dedicated busway with nine new bus stations between University Avenue in East Palo Alto and Middlefield Road in Redwood City. All transit service on the corridor would also serve Redwood City Transit Center and Caltrain. The busway could also serve places in the East Bay via the Dumbarton Highway Bridge. A dedicated busway would allow buses to travel quickly and reliably in under 15 minutes between East Palo Alto and destinations in Redwood City.
A continuous walking and bicycling trail
The busway would be paired with a 20-foot-wide paved walking and bicycling trail, creating a safe, comfortable place for people of all ages and abilities to ride their bike. This paved trail would include a new crossing for people walking, rolling and bicycling over US-101, connecting to the Bay Trail and other recreational opportunities.
The paved trail could be designed as a wide shared space or with separate spaces for different uses.
Multi-use Trail
Separated Bike/Pedestrian Trail
Take our survey to provide input on this design choice. Provide feedback through October 30!
Public Access and Community Spaces
The third element of the project is public access and community spaces. The project proposes to enhance connections to and across the corridor by adding 15 new access points for people walking or bicycling.
There will also be new walking and bicycling crossings at Ninth Avenue, Bay Road, US 101, and Belle Haven Community Campus.
Recreational opportunity areas along the corridor present opportunities for small community spaces such as mini parks, playgrounds, picnic areas or dog parks.
Phase II of community engagement is taking place September 9 - October 30. This is your opportunity to help the project team evaluate and refine options for the busway and trail project, before selecting a preferred alternative later this year.
Take our Survey
The second community survey is available from September 9, 2026 through October 30, 2026. Your input will help SamTrans better understand which design elements, connections, and community amenities are most important.
Attend a Community Event
Visit the project team at an upcoming community event to learn more about Reimagine Dumbarton, ask questions, and share your thoughts on the project.
- Saturday, Sept. 12 - Suburban Park Street Dance, 5:00 pm - 9:00 pm
- Dunsmuir Way, Menlo Park, CA 94025
- Saturday, Sept. 19 - Art Project at Magical Bridge Playground with Casa Circulo, 1:30 pm - 3:30 pm
- Redwood City Magical Bridge Playground, 938 Valota Rd, Redwood City, CA 94061, USA
- Sunday, Sept. 20 - North Fair Oaks Micro Mobility Day, 11:00 am - 2:00 pm
- Pal Center, 3399 Bay Rd., Redwood City, CA 94063
- Tuesday, Sept. 22 - Menlo Park City Council presentation 6:00 pm
- Menlo Park City Hall, 701 Laurel St. Menlo Park, CA 94025
- Wednesday, Sept. 23 - East Palo Alto Community Farmers’ Market, 8:30 am - 12:30 pm
- Bloomhouse, 2555 Pulgas Ave, East Palo Alto, CA 94303
- Thursday, Sept. 24 - North Fair Oaks Community Council presentation, 7:00 pm
- Fair Oaks Community Center, 2600 Middlefield Road, Redwood City CA, 94063
- Sunday, Sept. 27- Menlo Park Farmers Market, 9:00 am -1:00 pm
- Parking Lot on Chestnut St. (between Santa Cruz Ave. & Menlo Ave.)
- Saturday, Oct. 3 - Menlo Park Latino Heritage Month, 8:00 am - 1:00 pm
- Kelly Park, 100 Terminal Avenue, Menlo Park, CA, 94025
Project Resources
- SamTrans Board of Directors Project Update Presentation and Staff Report (August 2026)
- Phase 1 Community Outreach Summary Report
- Phase 1 Project Factsheet
- Phase 1 Community Meeting Presentation
Contact the Project Team
We want to hear from you. Community input is critical to Reimagine Dumbarton!
- Email the project team at dumbarton@samtrans.com
What is Reimagine Dumbarton?
Reimagine Dumbarton is a vision to transform a former freight rail line into a busway and trail for walking and bicycling spanning 5 miles between Redwood City and East Palo Alto on the Peninsula. Reimagine Dumbarton will identify opportunities to use the Dumbarton Corridor to provide access to community destinations, local and regional job centers, and the regional transportation network. The Reimagine Dumbarton study area includes the Dumbarton Corridor between University Avenue in East Palo Alto and Redwood City Transit Center. The feasibility study will determine how to best use the Corridor to create new bus, walking, and biking connections.
Why is Reimagine Dumbarton needed?
The Dumbarton Corridor is currently unused for transportation and is a barrier between communities.
This project offers a unique opportunity to reconnect communities and meet growing transportation demand. Since 2020, the number of trips on an average day between Redwood City and East Palo Alto has increased by more than 30%. These local trips, coupled with increases in regional traffic, result in increasing congestion.
A high-quality bus service responds to the community’s travel patterns and can be delivered more quickly and at lower cost than rail projects, while still providing fast and reliable transit. Busway projects are flexible as travel needs change and have been successful in attracting riders in many other regions.
What are the goals of Reimagine Dumbarton?
The goals of Reimagine Dumbarton are to:
- Improve connections between neighborhoods along the corridor
- Add new pedestrian and bicycle crossings
- Enhance speed and regional bus and Caltrain connections
- Support environmental sustainability
- Connect people to jobs and economic opportunity
- Preserve flexibility for future corridor use
What is SamTrans' role in this Project?
SamTrans operates public bus service in San Mateo County and owns the Dumbarton corridor right-of-way. SamTrans is leading the study to assess how reusing it can benefit communities along the Dumbarton Corridor.
How does Reimagine Dumbarton improve bicyclist and pedestrian conditions?
The Project design proposals, released in September 2026, include a continuous four-mile -long paved walking and bicycling trail parallel to a dedicated busway. Project designs also include 15 new public access points; four of these access points will provide a new crossing to help people walking and bicycling get from one side of the corridor to the other. These crossing locations are at Eighth/Ninth Avenue, Bay Road, US-101 and Belle Haven Community Campus.
What would the trail portion of the Project look like?
There are two possible designs for the new walking and biking trail – a multi-use/combined walking and biking trail or separate trails for people walking and biking. Both options would be paved and run parallel to the busway. Check out the Project Designs tab for more information.
Where are the proposed bus stations and how were those locations chosen?
Nine bus stations are proposed between Middlefield Road and University Avenue, spaced approximately 0.3 to 0.6 miles apart. These station locations were chosen to provide access to neighborhoods, employment areas, community destinations, intersecting transit services, and the broader bicycle and pedestrian network, while also considering stop spacing best practices, available access points, and other physical constraints.
- Fair Oaks Health Center/Middlefield Road
- Fifth Avenue
- Ninth Avenue
- Bay Road/Marsh Road
- Bohannon Drive
- Belle Haven Community Campus
- Chilco Street
- Willow Road
- University Avenue
Bus service will also extend to Redwood City Transit Center/Caltrain and destinations further into East Palo Alto beyond University Avenue. The exact location of routes and stops will be determined based on future community engagement.
How will this Project improve bus service?
A dedicated busway will make transit faster and more reliable than it is today.
The dedicated busway between Middlefield Road and University Avenue would provide a consistent travel time of approximately 13 minutes in both directions, without fluctuations during peak periods or because of traffic. The Project substantially improves transit travel times between destinations, with travel time on common trips dropping by as much as 74%; trips that currently take approximately 48 to 65 minutes would be reduced to approximately 17 to 39 minutes. This will make transit more attractive for riders and more efficient for SamTrans to operate.
What are the options for the Project to connect to Redwood City Transit Center/Caltrain?
The Project looked at many options for how to best connect to Redwood City Transit Center/Caltrain. At this time, we have two near-term options which both exit the busway at Middlefield Road. The Middlefield-Woodside option uses Woodside Road to access El Camino Real before terminating at the Transit Center. The Middlefield-Jefferson option accesses the Transit Center primarily via Middlefield Road and Jefferson Avenue, similar to current SamTrans route 296.
How many people do we think will use this Project once it’s built?
The Project is projected to generate significant growth in transit use in the Project area. Forecasts identify approximately 4,000 weekday transit boardings in the Corridor in the base year (2025) and up to 8,300 in 2050, including over 2,000 and 5,000 new transit trips in the base year and 2050, respectively. The Project alone is forecast to generate an increase in systemwide SamTrans ridership of up to 16 percent in year 2050. Increased ridership on Caltrain and other regional transit services is also expected.
The Iron Horse Trail, a walking and bicycling trail in the East Bay, has similar land uses and population density to the Dumbarton corridor. Average daily use at the most comparable location along the Iron Horse Trail is approximately 1,000 users, indicating the potential for meaningful daily bicycle and pedestrian use of the Dumbarton Corridor trail.
This Project will cross existing streets. How will that work?
New or modified signalized intersections will be installed where the busway crosses all streets. The traffic signal design and sequencing would include a phase for pedestrian and bicycle movements along the trail, across the crossing streets. Buses would be fitted with transit signal priority technology to help buses move quickly through intersections.
With these treatments, traffic simulation models and analysis show that the new busway intersections, including new signals, operate with minimal additional delay compared to today. The Project will work with local city and county partners to ensure smooth signal and traffic operations.
How has community input influenced the Project designs?
Community feedback received during Phase I of community engagement directly informed the design alternatives. During Phase I of community engagement, more than 1,000 community members throughout the corridor participated and shared their travel patterns, transportation challenges, and priorities for improving the Dumbarton Corridor. The project team used this input, together with technical analysis, to develop alternatives that respond to the community’s highest priorities while balancing engineering, operational, environmental, and cost considerations.
For example, the alternatives presented during Phase II:
- Improve regional transit connections by evaluating multiple ways to connect to Redwood City Transit Center and Caltrain, while providing convenient connections to regional bus services, including Dumbarton Express.
- Provide faster, more reliable transit through a dedicated busway that supports more direct service, increased frequency, and fewer transfers.
- Expand opportunities for walking and bicycling by including a shared-use trail, new pedestrian and bicycle crossings, and improved access to destinations along the corridor.
- Improve access to community destinations by positioning bus stations near neighborhoods, parks, community facilities, and regional transit, with shelters, lighting, and other rider amenities.
- Enhance the corridor as a community space by incorporating opportunities for public gathering and recreation spaces as well as landscaping, where feasible. All designs include privacy treatments such as landscaping and lighting to enhance safety.
If this vision for Reimagine Dumbarton is built, could the corridor still be used for rail service in the future?
Yes. This Project will not preclude the opportunity to convert the corridor to passenger rail in the future.
What is the timeline for Reimagine Dumbarton?
Reimagine Dumbarton is a multi-phase project. The current phase is a feasibility study, anticipated to be completed in spring 2027. After the feasibility study is complete, environmental studies and preliminary engineering take place, followed by final design. Pending funding availability, construction would start after 2031.
What will be the process for determining a final project design?
SamTrans will combine both technical analysis and community input to select a preferred alternative. Technical analysis will include review of existing mobility activity, ridership projections, existing and planned land use, and projected transit travel time savings. Community input will be used to identify current transportation needs, refine the draft alternatives, and understand community priorities.
What will happen after the Feasibility Study is complete?
Should the SamTrans Board of Directors adopt a preferred alternative at the end of the Reimagine Dumbarton feasibility study, the preferred alternative would then advance into environmental clearance, preliminary engineering/design, and eventually final engineering, design and permitting, followed by construction. SamTrans has already secured funding for the environmental clearance and preliminary engineering phases, should the project move forward.
What previous studies have been done on this corridor?
In 2018, SamTrans kicked off a process with Cross Bay Transit Partners, LLC (Facebook and Plenary Americas) to evaluate the technical and financial feasibility of a transit project along the Dumbarton rail bridge, connecting the Caltrain corridor at Redwood City to the East Bay. In Spring 2020, the project was put on hold due to the global pandemic. Facebook and SamTrans compiled and documented pre-environmental work of the alignment and technology options under consideration for the DRC Project.
This effort followed the completion of the 2017 Dumbarton Transportation Corridor Study, a feasibility study that evaluated potential multimodal transportation improvements within the Dumbarton Corridor and found high ridership potential for bus-based alternatives on the corridor.
How is Reimagine Dumbarton different from past studies?
The Dumbarton Corridor has been studied multiple times, mostly focused on regional passenger rail uses. This Study is focused on opportunities to provide new bus, pedestrian, and bicycle connections in the near-term, and is focused on San Mateo County only, west of University Avenue to Redwood City Transit Center. Building off community input received during previous studies, Reimagine Dumbarton focuses on creating safer, faster, and more sustainable connections in the near-term, without a new Bay crossing, to meet the needs of communities in southeast San Mateo County and regional travelers alike.
Bus service on the Dumbarton Corridor would include stations within Peninsula communities and will be operated with quieter and more sustainable zero emission vehicles, reducing noise and greenhouse gas emissions. While this study focuses on near-term bus, pedestrian, and bicycle improvements, it does not prevent train service from being explored along the Dumbarton Corridor in the future.